Skip Navigation LinksJob Special Provisions

The Job Special Provisions are revisions to the standard specifications and general provisions applicable to an individual project. Like the standard specifications, the JSPs contain information covering work methods, materials, measurements, or basis of payment. The JSPs take highest precedence over all material contained in the bidding documents.  This database contains the Standard JSP's, Non-Standard JSP's and LPA JSP's. 

 

 For questions about Job Special Provisions please contact Tim Oligschlaeger and LPA specific questions can be sent to Laura Ellen.

 

 

  
  
Explanatory_Notes
  
  
  
  
3 - or 4 - Strand High Tension Guard Cable
This JSP should be used when high tension guard cable is specified.
3/29/2010YesStandard
  
Accelerating the Completion of Closure Work (Incentive/Disincentive Clause)
This JSP is commonly known as A+B bidding.
12/5/2018YesStandard
  
ADA Compliance and Final Acceptance Of Constructed Facilities
This JSP is required on all projects with sidewalks or curb ramps.
1/17/2019YesStandard
  
Add Alternate Section (Per Project)
7/14/2016YesStandard
  
Additional Mobilization for Seeding
This is a fixed price, fixed qnty line item.  A qnty of 4 with a $600 cost for a total of $2400. This JSP is required for grading projects over 1 acre.  It may be used in smaller projects at the districts discretion.
6/25/2019YesNon Standard
  
Alternate for Pavements
This provision should be used for projects with 7,500 SY of continuous full depth pavement or 14,000 SY of full depth pavement at various locations.

1/4/2017YesStandard
  
Contract Liquidated Damages
This JSP is required on all projects except Job Order Contracts and must be JSP B in the set of JSPs.
4/1/2015YesStandard
  
Contractor Quality Control
This JSP is for use on all projects EXCEPT for JOCs, projects with Quality Management JSP, and other very small projects.  See spreadsheet from the Construction Division to determine if your project has been selected for this JSP or has received a waiver.
4/20/2018YesNon Standard
  
Contractor Quality Control For Plant Mix Bituminous Surface Leveling 
Use when project includes bid item 402-05.20 - Bituminous Pavement Mixture PG64-22 (Surface Leveling).  10/1/15 QM JSP or QC JSP are not required unless other types of asphalt or concrete are in project.
10/6/2015YesNon Standard
  
Emergency Provisions and Incident Management
This JSP is required on all project and provides contact inform for the local law enforcement and fire departments.
4/19/2018YesStandard
  
General - Federal
05/30/19 - Revised reference for Standard Plans to 2019 Standard Plans and updated references to MoDOT's web pages.
05/22/18 -Changed JSP letter D
5/30/2019YesStandard
  
General - State
05/30/19 - E - Revised reference for Standard Plans to 2019 Standard Plans and updated references to MoDOT's web pages.
05/22/18 -Changed JSP letter to D
5/30/2019YesStandard
  
Law Enforement In The Workzone
For use on projects which will include workzone enforcment.
3/17/2015YesStandard
  
Liquidated Damages / Liquidated Savings Specified
This provision is for use to motivate the contractor to complete the work in a specific time frame as set up by the District. The description of the work should be complete and directly related to the Damage/Savings amount set up.
10/5/2007YesStandard
  
Liquidated Damages for Winter Months
This JSP should be used on projects where the primary work can be performed during the winter months, such as bridge construction.
4/30/2019YesStandard
  
Liquidated Damages Specified
This JSP should be used when there is milestone date that must be met such as opening the road to traffic before a special event in the area.
10/5/2007YesStandard
  
Liquidated Savings Specified
For use to motivate the contractor to complete the work in a specific time frame as set up by the District. Ensure that the description of the work in question is complete as possible and directly related to the Damage/Savings amount set up.
10/5/2007YesStandard
  
MoDOT’S Construction Workforce Program
Required for all projects listed on the Construction Workforce Program Pilot Project List:

Bidding and Contract : Shared Documents : Letting_Information>QC_QM_WF_Project_List.xlsx

This site will not work for external users.
8/19/2016YesNon Standard
  
Optional Pavements
This provision should be used for projects which do not meet the criteria for Alt Pavements, specifically those with less than 7,500 SY of continuous full depth pavement or less than 14,000 SY of full depth pavement at various locations.
1/4/2017YesStandard
  
Optional Shoulder
This is to be used on shouldering projects that will allow for a concrete option when bituminous asphalt is specified.

3/19/2013YesStandard
  
Optional Temporary Pavement Marking Paint
This JSP provides the contractor with the option to either complete all Permanent Pavement Marking Paint prior to the time limits specified or to apply Temporary Pavement Marking Paint.
7/3/2019YesNon Standard
  
Optional Traffic Signal Detectors
To be used when Optional Traffic Signal Detectors are specified.
1/3/2011YesStandard
  
Project Contact for Contractor/Bidder Questions
This JSP is required on all projects.
4/19/2018YesStandard
  
Quality Management
Add this JSP to all projects identified as complex.  See spreadsheet from Construction Division for a list of projects that will require the Quality Management JSP.
7/1/2014YesNon Standard
  
Removal and Delivery of Existing Signs
Use this JSP when any existing roadway signs are to be removed from the project.
7/12/2019YesStandard
  
Roadway Job Special Provision Formatting Instructions
This format is to be used by all when writing JSPs in order to create uniformity in project proposals.
4/3/2018YesStandard
  
Roadway Job Special Provision Template
This template is to be used for Roadway Job Special Provisions.  Choose the appropriate signature block and provide the necessary provisions according to the template provided.
7/1/2019YesStandard
  
Roadway JSP Instructions
These instructions provide guidance on how to create a set of JSPs using the new formatting setup. (Internal use only)
YesStandard
  
Seal Coat Completion of Work
To be used in Seal Coat projects which span multiple seasons.  Developed for the 2016 Seal coat program.
6/26/2015YesStandard
  
Supplemental Revisions
JSP-1801H: 05/30/19 - Removed sections 106 and 616 and added them to the Spec Book.
JSP-1801G: 02/05/19 - Removed section 610.4.5.4 as it was updated in the Spec Book.
5/30/2019YesStandard
  
Tree Clearing Restriction
* Central Office Environmental Section should be consulted prior to using this JSP.
9/9/2015YesStandard
  
Utilities
12/1/2016YesStandard
  
Winter Months Requirements
To be used for overlay projects that span multiple construction seasons.  Developed for the CLC program.
4/30/2019YesStandard
  
Work Zone Traffic Management
This JSP needs to be inserted into every project as "JSP C" in the set of JSPs.
7/1/2019YesStandard